No chance..sorry..2-3 weeks for the framing (if it̢۪s a good crew) add a week for a cut roof if you don't have trusses. Then 1-3 days for the roofers...and only then can the Elc, Plum, and Duct start. Then inspection (hope the inspectors not behind) then the framers come back for cleanup/windows, then stairs, insulators, drywall, trim carpenter, flooring, cabinets, railings and last painters. By now the exterior should be finished they start after the windows are in. So my guess if everything runs smooth Early December but most likely the first of next year. Sorry